12月11日,廣東省口岸辦正式簽發(fā)文件,同意惠州港荃灣港區(qū)煤炭碼頭一期工程正式對(duì)外開放,標(biāo)志著惠州荃灣煤炭港作為全國首個(gè)大型綠色示范公用煤炭碼頭全面投入生產(chǎn)作業(yè)當(dāng)天,惠州市口岸辦組織了廣東省、深圳市、惠州市的海關(guān)、海事、邊檢、口岸及政府部門等12家單位對(duì)惠州荃灣港煤炭碼頭一期工程進(jìn)行口岸開放驗(yàn)收
項(xiàng)目驗(yàn)收專家組和與會(huì)代表進(jìn)行了現(xiàn)場(chǎng)查驗(yàn),并在港區(qū)綜合樓5樓會(huì)議室召開了驗(yàn)收會(huì)議會(huì)后,廣東省口岸辦簽發(fā)了《廣東省口岸辦關(guān)于惠州港荃灣港區(qū)煤炭碼頭一期工程對(duì)外開放的批復(fù)》
The project acceptance expert group and the participating representatives conducted on-site inspection and held an acceptance meeting in the conference room on the 5th floor of the port complex building. After the meeting, Guangdong port office issued the reply of Guangdong port office on the opening up of the phase I project of the coal wharf in the Tsuen Wan port area of Huizhou Port